(Summary description)1, scaffolding safety net must have a sound construction plan, and approved by the person in charge of enterprise technology.

Safety technical requirements for scaffolding safety nets

(Summary description)1, scaffolding safety net must have a sound construction plan, and approved by the person in charge of enterprise technology.

Information

  1, scaffolding safety net must have a sound construction plan, and approved by the person in charge of enterprise technology.

Scaffolding safety net

  2, must have a sound security measures, according to the provisions set up safety nets, protective railing, block feet.

  3, scaffolding safety net operators up and down the shelf, there must ensure the safety of escalators, ladders, ramps.

  4. There must be good anti-electricity and lightning protection devices. Steel scaffolding should be reliably grounded. The scaffolding higher than the surrounding buildings should be equipped with lightning protection devices.

  5, the scaffold must be safety nets predetermined set sweep shot, the wall pieces and scissors and ensure a firm frame body.

  6, scaffold boards to shop for, shop steady, shall not stay the probe panel, to ensure that there are three supporting points and lashing firm.

  7. The scaffolding safety net must be checked at any time during the erection and use of the scaffolding, the garbage on the scaffolding body must be removed frequently, and the load on the scaffolding should be controlled.

  8. The scaffolding should be inspected in detail after the project resumes work and the weather is wind, rain and snow. If it is found that the poles sink, hang in the air, loose joints, and the shelf is skewed, they should be dealt with in time.

  9. When the scaffolding safety net encounters strong wind or fog and heavy rain above level 6, the operation at high places should be suspended, and anti-skid measures should be taken for the operation of the scaffolding after rain and snow.

  10, after completion of scaffolding erection and acceptance should be checked before use after inspection acceptance.

  11. When the scaffolding safety net is operated in multiple layers at the same time, a reliable protective shed should be set up between each operation layer to prevent the falling objects from the upper layer from injuring the workers on the lower layer.

Keyword:

Scan the QR code to read on your phone

Related News

Shandong Antai Chemical Fiber Products Co., Ltd.

Copyright © 2021  Shandong Antai Chemical Fiber Products Co., Ltd.  All Rights Reserved   鲁ICP备20018353号-1   Powered by:www.300.cn